Australia's first offshore wind auction is three months in. Here's what's on offer, who can bid, and what could still change it
Australia has no offshore wind farm yet. Since 26 August, Victoria has been asking developers to bid for the first 2 GW off Gippsland, backed by a 20-year contract and a payment for being available. Bids close in August 2027 and first power is due in 2034. On Saturday, Victoria votes.
What Victoria is buying
On 26 August 2026, Victoria opened the request for proposals for its first 2 GW of offshore wind, which the government says is enough for about 1.5 million homes. It's Australia's first offshore wind auction. The round runs for twelve months, closing in August 2027, with contracts expected to be awarded in 2028, construction from 2032 and first power in 2034. Bids are judged on value for money, deliverability and benefits for local workers, businesses and communities.
It is the first step towards targets Victoria set in 2022 and legislated in March 2024: at least 2 GW of offshore wind by 2032, 4 GW by 2035 and 9 GW by 2040. On the auction's own timetable, the first target slips: 2 GW contracted in 2028 and generating from 2034. RenewEconomy describes the programme as roughly two years behind.
From targets to first power: the timetable
- March 2022Targets set: 2 GW by 2032, 4 GW by 2035, 9 GW by 2040
- March 2024The targets written into law
- 26 August 2026The auction opens: up to 2 GW off Gippsland
- 28 November 2026Victoria votes
- August 2027Bids close
- 2028Contracts awarded
- From 2032Construction
- 2034First power
- By July 2035Loy Yang A, Victoria's largest coal plant, closes
- 20409 GW target
The deal on offer
A winning project gets two things. The first is a revenue-neutral contract for difference lasting 20 years: if the farm's market revenue falls below an agreed strike price, the contract tops it up, and if it rises above, the project pays back. Twenty years is longer than the 10 to 15 years usual elsewhere, and the government says it is there to take market price risk off the table. The second is an availability payment, a fixed, regular sum paid once the farm is operating.
Lawyers at Herbert Smith Freehills Kramer describe the contract as a regional reference PPA: settled against the output of a reference fleet of generators rather than the farm's own. The contracts are expected to move into the federal Electricity Services Entry Mechanism (ESEM), the successor to the Capacity Investment Scheme, which the auction guide expects to be in place by the end of 2027. How the costs are split between Canberra and Victoria hasn't been said, and neither has the strike price.
Who can bid
Only projects in Victoria's declared offshore wind areas, holding a Commonwealth feasibility licence, can take part. Off Gippsland, the federal energy department lists nine active feasibility licences, with more than 20 GW proposed between them. The field has narrowed since the first licences were granted: BlueFloat Energy surrendered Gippsland Dawn in July 2025, RWE surrendered Kent in October 2025, and the partners behind Gippsland Skies, including AGL and Mainstream, surrendered theirs in January 2026.
| Project | Developer | Proposed GW |
|---|---|---|
| Star of the South | Southerly Ten | 2.2 |
| Kut-Wut Brataualung | Southerly Ten | 2.2 |
| Gippsland 1 | Ørsted | 2.8 |
| Gippsland 2 | Ørsted | 2.0 |
| High Sea Wind | Ocean Winds | 1.3 |
| Blue Mackerel | JERA Nex bp | 1.0 |
| Great Eastern Offshore Wind | Corio Generation | – |
Projects named in the Gippsland Offshore Wind Alliance's sector plan (June 2026), with its capacities. The federal register lists nine active licences off Gippsland; the plan names these seven.
With room for only 2 GW, the round is likely to be won by a single project. Star of the South, at 2.2 GW, is often described as the most advanced. In October, the Victorian parts of Ocean Winds' High Sea Wind cleared federal environmental assessment, while the offshore part, of up to 117 turbines, was declared a controlled action that needs full assessment.
Getting the power ashore
VicGrid, which took over Victorian transmission planning from the market operator in November 2025, is planning the connection for the first 2 GW: cables through the Gippsland Shoreline Renewable Energy Zone, declared in May 2026, to the switchyard at Loy Yang power station. Building on the old coal site's grid connection is deliberate: Loy Yang A is due to close by July 2035, a year after the first offshore power is due.
What could still change it
- The price. The strike price isn't public. The Australian Energy Market Operator puts offshore wind at about two-thirds more expensive than onshore wind to build and connect, and at the All-Energy conference in Melbourne in October, Iberdrola Australia called conditions for global investors "at the tipping point".
- Ports and supply chain. Building offshore wind needs a port that can handle turbines of this size; port capacity was raised at the same conference as a cost Victoria still has to solve.
- Politics. Victorians vote on Saturday 28 November. The Liberal-Nationals opposition has backed the offshore wind plan; One Nation has said it would scrap it. And the federal ESEM, which the contracts are meant to join, still needs ministerial approval, expected by the end of 2026.
On Windfolio's map, Australia's offshore wind projects and the federal licence areas sit together under Australia's layers, with each project's developer and proposed capacity.
Sources
- Victorian Government: the Premier's media release of 26 August 2026, "Offshore wind powering ahead" (2 GW, 1.5 million homes, assessment criteria, August 2027 close, 2028 award, ESEM); Victoria's legislated offshore wind targets (2 GW by 2032, 4 GW by 2035, 9 GW by 2040).
- Department of Climate Change, Energy, the Environment and Water: the Gippsland declared offshore wind area (nine active feasibility licences; the surrenders of Gippsland Dawn, Kent and Gippsland Skies).
- Gippsland Offshore Wind Alliance, Gippsland Offshore Wind Sector Plan (June 2026): the projects and capacities in the table.
- RenewEconomy, 25 August, 6 October and 30 October 2026 (the auction's launch, the contract terms and the auction guide, High Sea Wind's assessment, the All-Energy conference); WattClarity, 7 October 2026 (contract structure); Herbert Smith Freehills Kramer via Legal 500, 28 August 2026 (the reference PPA, VicGrid's transmission plan).
- Victorian Electoral Commission: the state election on Saturday 28 November 2026.
- Written 25 November 2026. The auction guide's terms may be refined as the tender documents and ESEM's design are finalised. Questions: mail@revolutionenergy.net.
Where sources differ: one law-firm note says the 2 GW could come from both declared areas, Gippsland and the Southern Ocean off western Victoria; the government's guide and other reports speak of Gippsland, where the transmission is planned.
Free to reuse with credit. Please cite: